Preparation of tender design & documents, project management and Contract administration of Marala (7.64MW) Hydropower Project

Project Name:

Preparation of tender design & documents, project management and Contract administration of Marala (7.64MW) Hydropower Project

Location Country/ Province/ Division:

RD 2+500, Uper Chenab Canal Main Marala, Punjab, Pakistan.

Client:

Irrigation & Power Department Government of Pakistan.

Implementation Start / Expected Completion:

May, 2009 to June 2016

This is a run of river type hydropower project. The project site is located at RD 2+500 of Upper Chenab Canal Main approximately 760 Meter downstream of the existing head regulator at RD 0+300 & about 25 km from Sialkot Town. The powerhouse & spillway is placed adjacently along the same axis & will be constructed in the By Pass. Powerhouse is equipped with four Horizontal Kaplan Turbines with a combined capacity of 7.2MW. The available design discharge is 350m3/s, and rated head net 2.56m. The total energy output will be 48.52 GWh and the implementation time is estimated as 52 months.